Ādisōke Construction Update – April 26, 2023

Work continues to progress well on site. Pouring of the main floor of the facility is now complete and pouring of the second floor is progressing well. In the coming weeks, columns from the second level to the third level of the facility will be poured and work will begin on the third floor.

In honour of the National Day of Mourning, the Contractor will be conducting a mock evacuation of the site on Friday, April 28 at approximately 9 am. Residents in the area might hear horn sounds at this time.