Progress continues on the levels of Ādisōke. Pouring of the third floor is now complete, and pouring of the fourth floor is underway. The framework for the fifth level is now commencing.
Additionally, 17 of the 25 post-tensioned beams for the facility have now been completed to give extra strength to the floor slabs. Post-tensioning is a method of reinforcing concrete with high-strength steel strands. The use of post-tensioned beams in Ādisōke will ensure the durability of the facility for decades to come.
In the coming weeks, the fourth floor will finish being poured, and pouring of the fifth and final floor will begin.