The main floor of the facility continues to take shape. The P1 slab is now complete with its last concrete pour. Electrical wiring and mechanical plumbing rough-in have commenced on the P1 and P2 level. In the coming days, the L1 suspended concrete slabs will be formed and poured. Backfilling and waterproofing operations are continuing around the perimeter of the building. The installation of site services, such as the water main, sanitary and storm sewer lines, are also ongoing.