June was another busy month at the Ādisōke project site. The second floor is now finished being poured, and the third floor is over 75 per cent complete. Falsework for the fourth level of the facility is ongoing.
In the coming weeks, the third floor will finish being poured, and pouring of the fourth floor will begin.