Big news for the Ādisōke project site since our last update! All the branch columns were completed in February, which is an exciting milestone as we are starting to really see the building take shape. The Level 1 mezzanine west structure was also completed in February.
Outside, work is ongoing on the façade steel, plywood and panels. Some stonework is also underway.
Inside the building, masonry work is ongoing, as well as mechanical and electrical rough-ins, and work on the feature staircase.