The Ādisōke project will soon reach an exciting milestone. The fifth floor of the facility is almost completely poured, and in the coming days, we will celebrate the completion of all five levels of the facility! Click here to watch a video of a recent concrete pour that took place in September.
In the weeks ahead, structural steel work will continue, as well as the stressing of post-tensioned beams. Building mechanical and electrical work will also take place.