News Category: Construction

Ādisōke Construction Update – November 1, 2024

October was a productive month for Ādisōke. Nearly all the windows have now been installed, including the large auditorium windows. Scaffolding work is advancing, both inside and outside the facility, and stonework installation is ongoing. If you’ve passed by the site recently, you might have noticed that the east tower crane has now been removed.

Read More »

Ādisōke Construction Update – September 27, 2024

September was another busy month at the Ādisōke project site. Over the past few weeks, work continued to advance on the installation of the windows, as well as structural steel work on the roof. In the coming weeks, waterproofing work will continue, and the building will soon be watertight. The installation of the auditorium windows

Read More »

Ādisōke Construction Update – August 27, 2024

There’s a lot to be excited about at the Ādisōke site! Work continues to progress on the building envelope, including the installation of the air vapour barrier, insulation and exterior stone. Significant progress has been made on the installation of the windows, as well as the skylights.   Inside the building, masonry and framing work

Read More »

July 2024 Update

News from the rooftop A lot has happened at the Ādisōke project site since our last update. We’ll start from the top: significant progress has been made on Ādisōke’s curved roof. The wooden structural beams have all been installed and the paneling is also complete. Photo 1: Aerial view of the Ādisōke facility showing the wooden

Read More »

Adisoke Construction Update – July 5, 2024

The Ādisōke building envelope is continuing to advance. Over the last few weeks, progress was made on the installation of the façade window framing, scaffolding on the building face and vapour barrier on the roof. Inside the facility, mechanical, electrical, plumbing and masonry work is ongoing.   In the coming weeks, work will continue to progress

Read More »

Ādisōke Construction Update – June 10, 2024

Since our last update, the Ādisōke project reached a milestone: the paneling for the wooden roof is now complete! The installation of the air vapour barrier for the roof is now underway. Work continues to advance on the building envelope, including the installation of scaffolding and envelope finishes. Inside the building, masonry work and wall

Read More »

Ādisōke Construction Update – May 2, 2024

The Ādisōke project site has been busy over the past few weeks. The wooden roof structural beams have all been installed and roof paneling is almost finished. Structural steel work for the feature staircase and atrium is also complete. In the weeks ahead, façade steel installation will continue, as well as glazing, sheathing and exterior

Read More »

Ādisōke Construction Update – April 5, 2024

We are happy to report that several sections of the feature stairs have been installed since our last update! Also inside, the mechanical room on the fifth floor has been completed, and equipment moved in. Over the last month, there was ongoing mechanical, electrical, plumbing and masonry work on parking levels 1 and 2.  Outside,

Read More »

March 2024 Update

Indigenous Public Artists announced Did you know that Indigenous art will be featured throughout Ādisōke? This week, we announced that artists from across Canada have been selected through the Ādisōke Indigenous Public Art program. They will produce the following art for the facility: Dee Barsy, Skownan First Nation, based in Winnipeg: interior Pimisi entrance Mary

Read More »

Ādisōke Construction Update – March 8, 2024

Big news for the Ādisōke project site since our last update! All the branch columns were completed in February, which is an exciting milestone as we are starting to really see the building take shape. The Level 1 mezzanine west structure was also completed in February.  Outside, work is ongoing on the façade steel, plywood

Read More »