Year in Review 2024
Watch our year in review video to see the progress of Ādisōke over the last 12 months.
Watch our year in review video to see the progress of Ādisōke over the last 12 months.
Throughout November, work progressed on the exterior of the building, which included the installation of all of Ādisōke’s windows, more insulation and stonework. At the corner of Albert and Commissioner streets, some of the scaffolding has come down to reveal a part of the building’s beautiful facade. Inside Ādisōke, wall construction will continue, along with
Windows, walls and waterproofing From windows, to walls, to waterproofing, the last few months have been exceptionally busy at the Ādisōke project site. In September, the breathtaking windows for the auditorium were installed. These are the largest windows for the facility and represent an exciting milestone for the project. Work also continued to progress on
October was a productive month for Ādisōke. Nearly all the windows have now been installed, including the large auditorium windows. Scaffolding work is advancing, both inside and outside the facility, and stonework installation is ongoing. If you’ve passed by the site recently, you might have noticed that the east tower crane has now been removed.
September was another busy month at the Ādisōke project site. Over the past few weeks, work continued to advance on the installation of the windows, as well as structural steel work on the roof. In the coming weeks, waterproofing work will continue, and the building will soon be watertight. The installation of the auditorium windows
There’s a lot to be excited about at the Ādisōke site! Work continues to progress on the building envelope, including the installation of the air vapour barrier, insulation and exterior stone. Significant progress has been made on the installation of the windows, as well as the skylights. Inside the building, masonry and framing work
News from the rooftop A lot has happened at the Ādisōke project site since our last update. We’ll start from the top: significant progress has been made on Ādisōke’s curved roof. The wooden structural beams have all been installed and the paneling is also complete. Photo 1: Aerial view of the Ādisōke facility showing the wooden
The Ādisōke building envelope is continuing to advance. Over the last few weeks, progress was made on the installation of the façade window framing, scaffolding on the building face and vapour barrier on the roof. Inside the facility, mechanical, electrical, plumbing and masonry work is ongoing. In the coming weeks, work will continue to progress
Since our last update, the Ādisōke project reached a milestone: the paneling for the wooden roof is now complete! The installation of the air vapour barrier for the roof is now underway. Work continues to advance on the building envelope, including the installation of scaffolding and envelope finishes. Inside the building, masonry work and wall
The Ādisōke project site has been busy over the past few weeks. The wooden roof structural beams have all been installed and roof paneling is almost finished. Structural steel work for the feature staircase and atrium is also complete. In the weeks ahead, façade steel installation will continue, as well as glazing, sheathing and exterior