Search
Close this search box.

News Category: Construction

Ādisōke Construction Update – May 2, 2024

The Ādisōke project site has been busy over the past few weeks. The wooden roof structural beams have all been installed and roof paneling is almost finished. Structural steel work for the feature staircase and atrium is also complete. In the weeks ahead, façade steel installation will continue, as well as glazing, sheathing and exterior

Read More »

Ādisōke Construction Update – April 5, 2024

We are happy to report that several sections of the feature stairs have been installed since our last update! Also inside, the mechanical room on the fifth floor has been completed, and equipment moved in. Over the last month, there was ongoing mechanical, electrical, plumbing and masonry work on parking levels 1 and 2.  Outside,

Read More »

March 2024 Update

Indigenous Public Artists announced Did you know that Indigenous art will be featured throughout Ādisōke? This week, we announced that artists from across Canada have been selected through the Ādisōke Indigenous Public Art program. They will produce the following art for the facility: Dee Barsy, Skownan First Nation, based in Winnipeg: interior Pimisi entrance Mary

Read More »

Ādisōke Construction Update – March 8, 2024

Big news for the Ādisōke project site since our last update! All the branch columns were completed in February, which is an exciting milestone as we are starting to really see the building take shape. The Level 1 mezzanine west structure was also completed in February.  Outside, work is ongoing on the façade steel, plywood

Read More »

Ādisōke Construction Update – February 8, 2024

The Ādisōke project site is seeing continued work on the roof panelling as well as the branch columns. The installation of façade steel along the exterior of the building is also almost complete. Inside the building, vapour barrier work is continuing, as well as partition framing. Electrical and mechanical rough-in work remains ongoing.

Read More »

Ādisōke Construction Update – January 12, 2024

The new year is off to a busy start at the Ādisōke project site. The installation of façade steel along the exterior of the building continues to progress well, and the installation of the wooden beams and roof panelling has begun. In the coming weeks, work on the building’s façade will continue, and the tree-like

Read More »

Ādisōke Fall Update

ĀDISŌKE CELEBRATES COMPLETION OF FLOORS  This fall was an exciting season for the Ādisōke project! In October, we reached a major milestone: the completion of the pouring of all five floors, also known as the “topping off” of the facility. To celebrate, an event was held at the Ādisōke project site, where the partners each

Read More »

Ādisōke Construction Update – December 6, 2023

The last month of 2023 will be a busy one as work continues to progress at the Ādisōke project site. In November, the vertical concrete elements were completed, and work on the building’s façade continued. The installation of the “tree-like” branch columns also began on the upper floors. In the coming weeks, façade work will

Read More »

Ādisōke Construction Update – November 2, 2023

The Ādisōke project recently recached a major milestone: the completion of the pouring of all five floors! To celebrate, we held a milestone event at the project site on October 18. You can read more about the event here. In addition to the completion of the floors, all post-tensioned beam work is now finished. In

Read More »

Ādisōke Construction Update – October 6 2023

The Ādisōke project will soon reach an exciting milestone. The fifth floor of the facility is almost completely poured, and in the coming days, we will celebrate the completion of all five levels of the facility! Click here to watch a video of a recent concrete pour that took place in September. In the weeks ahead, structural

Read More »
Skip to content