News Category: Construction

Construction Update – June 6, 2025

In April, on the exterior of the building, construction crews continue with stonework on the west and north sides of the building. Both the exterior wood siding and landscaping are now underway, bringing that distinct look and feel we’ve been waiting for to the site. As the scaffolding comes down, the full façade of the

Read More »

Construction Update – May 6, 2025

In April, crews continued to add the finishing touches on the exterior of the building, with insulation and stonework being added to the west and north sides of Ādisōke. On the inside, masonry is in full force as the walls are framed and the components to service all the utilities are laid out. The wood

Read More »

Construction Update – April 9, 2025

In March, the exterior of the building continued to see more scaffolding come down and stonework go up. The walls are moving closer to their final look and the progress has been stunning so far. Inside the building, all the important connections for the walls and utilities are still progressing as crews try to make

Read More »

Construction Update – March 3, 2025

In February, work on the exterior of the building progressed with more insulation going in and some stonework being installed on the north and west sides. Waterproofing for all floors is also underway. On the inside, framing and masonry are underway as the individual rooms in the facility are starting to come to life. Another

Read More »

Construction Update – February 10, 2025

In January, work continued on the outside walls of the building as some of the scaffolding has come down, revealing completed sections of the exterior. Important electrical and other utility work continued on the interior, which has allowed for some framing and drywalling of interior walls to start.

Read More »

Construction Update – January 8, 2025

In December, work on the exterior of the building continued to move along with the final installation of all the windows. Crews also continue to install various elements of the exterior walls, like stonework and insulation, to better insulate the building. On the inside, all the internal components started coming together, with electrical, mechanical and

Read More »

Construction Update – December 3, 2024

Throughout November, work progressed on the exterior of the building, which included the installation of all of Ādisōke’s windows, more insulation and stonework.  At the corner of Albert and Commissioner streets, some of the scaffolding has come down to reveal a part of the building’s beautiful facade. Inside Ādisōke, wall construction will continue, along with

Read More »

Ādisōke Fall 2024 Update

Windows, walls and waterproofing From windows, to walls, to waterproofing, the last few months have been exceptionally busy at the Ādisōke project site. In September, the breathtaking windows for the auditorium were installed. These are the largest windows for the facility and represent an exciting milestone for the project. Work also continued to progress on

Read More »

Ādisōke Construction Update – November 1, 2024

October was a productive month for Ādisōke. Nearly all the windows have now been installed, including the large auditorium windows. Scaffolding work is advancing, both inside and outside the facility, and stonework installation is ongoing. If you’ve passed by the site recently, you might have noticed that the east tower crane has now been removed.

Read More »
Skip to content