News Category: Construction

Ādisōke Construction Update – November 2, 2023

The Ādisōke project recently recached a major milestone: the completion of the pouring of all five floors! To celebrate, we held a milestone event at the project site on October 18. You can read more about the event here. In addition to the completion of the floors, all post-tensioned beam work is now finished. In

Read More »

Ādisōke Construction Update – October 6 2023

The Ādisōke project will soon reach an exciting milestone. The fifth floor of the facility is almost completely poured, and in the coming days, we will celebrate the completion of all five levels of the facility! Click here to watch a video of a recent concrete pour that took place in September. In the weeks ahead, structural

Read More »

Ādisōke Summer Update

Ādisōke Reaches New Levels! The concrete was flowing at the Ādisōke project site this past summer as we continued to make progress on pouring the floors. Four of the levels are now complete, and work is underway on the fifth and final floor! Click here to watch a video of one of our recent concrete

Read More »

Ādisōke Construction Update – September 7, 2023

Work continues to progress well on Ādisōke. Over the last few weeks, several concrete pours took place. The fourth floor was recently completed, and work on the fifth and final floor is underway. The installation of structural steel continues, and 21 of the 25 post-tensioned beams are now complete. In the coming days, pouring of

Read More »

Ādisōke Construction Update – August 2, 2023

Progress continues on the levels of Ādisōke. Pouring of the third floor is now complete, and pouring of the fourth floor is underway. The framework for the fifth level is now commencing. Additionally, 17 of the 25 post-tensioned beams for the facility have now been completed to give extra strength to the floor slabs. Post-tensioning

Read More »

Ādisōke Construction Update – July 6, 2023

June was another busy month at the Ādisōke project site. The second floor is now finished being poured, and the third floor is over 75 per cent complete. Falsework for the fourth level of the facility is ongoing. In the coming weeks, the third floor will finish being poured, and pouring of the fourth floor

Read More »

Ādisōke Spring Update

Floor-ious Progress on Ādisōke… If you’ve passed by the Ādisōke project site recently, there’s a good chance you witnessed a beehive of activity as the building continues to grow into the sky! The site has been busy with several concrete pours, and significant progress has been made on the first three floors of the facility.

Read More »

Ādisōke Construction Update – May 31, 2023

May was a busy and productive month at the Ādisōke project site. Pouring of the second floor is nearly complete and work is progressing well on the third floor. Installation of the elevator shafts are also underway. In the coming weeks, pouring of the second floor will be completed, and the third floor will start

Read More »

Ādisōke Construction Update – April 26, 2023

Work continues to progress well on site. Pouring of the main floor of the facility is now complete and pouring of the second floor is progressing well. In the coming weeks, columns from the second level to the third level of the facility will be poured and work will begin on the third floor. In

Read More »

Ādisōke Construction Updates – April 6, 2023

Pouring of the first floor of the facility continues to progress, with over 60 per cent now complete. In the coming days, the floor of the main level will continue to be poured, as well as the columns from the main level to the second level. Pouring of the second floor will also begin, and

Read More »
Skip to content