News Category: Construction

Construction Update – March 3, 2025

In February, work on the exterior of the building progressed with more insulation going in and some stonework being installed on the north and west sides. Waterproofing for all floors is also underway. On the inside, framing and masonry are underway as the individual rooms in the facility are starting to come to life. Another

Read More »

Construction Update – February 10, 2025

In January, work continued on the outside walls of the building as some of the scaffolding has come down, revealing completed sections of the exterior. Important electrical and other utility work continued on the interior, which has allowed for some framing and drywalling of interior walls to start.

Read More »

Construction Update – January 8, 2025

In December, work on the exterior of the building continued to move along with the final installation of all the windows. Crews also continue to install various elements of the exterior walls, like stonework and insulation, to better insulate the building. On the inside, all the internal components started coming together, with electrical, mechanical and

Read More »

Construction Update – December 3, 2024

Throughout November, work progressed on the exterior of the building, which included the installation of all of Ādisōke’s windows, more insulation and stonework.  At the corner of Albert and Commissioner streets, some of the scaffolding has come down to reveal a part of the building’s beautiful facade. Inside Ādisōke, wall construction will continue, along with

Read More »

Ādisōke Fall 2024 Update

Windows, walls and waterproofing From windows, to walls, to waterproofing, the last few months have been exceptionally busy at the Ādisōke project site. In September, the breathtaking windows for the auditorium were installed. These are the largest windows for the facility and represent an exciting milestone for the project. Work also continued to progress on

Read More »

Ādisōke Construction Update – November 1, 2024

October was a productive month for Ādisōke. Nearly all the windows have now been installed, including the large auditorium windows. Scaffolding work is advancing, both inside and outside the facility, and stonework installation is ongoing. If you’ve passed by the site recently, you might have noticed that the east tower crane has now been removed.

Read More »

Ādisōke Construction Update – September 27, 2024

September was another busy month at the Ādisōke project site. Over the past few weeks, work continued to advance on the installation of the windows, as well as structural steel work on the roof. In the coming weeks, waterproofing work will continue, and the building will soon be watertight. The installation of the auditorium windows

Read More »

Ādisōke Construction Update – August 27, 2024

There’s a lot to be excited about at the Ādisōke site! Work continues to progress on the building envelope, including the installation of the air vapour barrier, insulation and exterior stone. Significant progress has been made on the installation of the windows, as well as the skylights.   Inside the building, masonry and framing work

Read More »

July 2024 Update

News from the rooftop A lot has happened at the Ādisōke project site since our last update. We’ll start from the top: significant progress has been made on Ādisōke’s curved roof. The wooden structural beams have all been installed and the paneling is also complete. Photo 1: Aerial view of the Ādisōke facility showing the wooden

Read More »
Skip to content